What Is AQL (Acceptance Quality Limit)? What Does AQL 2.5 Mean for a Chinese Order?

What does AQL 2.5 actually mean?

It is a quality level used to look up a sampling plan in a standard's tables. The international standard is ISO 2859-1. China's national version is GB/T 2828.1. The plan you get gives two things: how many units to draw from the batch, and the largest number of defects of a given class the sample may contain before the batch fails.

AQL is often read as the buyer agreeing to take a set share of bad goods, or as proof that a batch which passes has no problems. Neither is right. Sampling carries risk both ways. A poor batch can pass, a good batch can fail, and units nobody drew can still be defective. And when a batch passes, the defective units the inspector found still have to be dealt with.

What else does a sampling plan need besides the AQL number?

Writing "AQL 2.5" alone leaves most of the plan open. A complete plan answers these points:

PointWhat to agree
StandardWhich sampling standard and which edition, named in the contract. GB/T standards are recommended national standards: under the Standardization Law only mandatory standards must be followed (art. 2), so name the one you want.
BatchWhat counts as one batch or lot, for example one production run or one shipment.
Inspection levelThe level, which sets how many units are drawn.
Defect classesWritten definitions of critical, major and minor defects, with photos where you can.
LimitsA separate AQL or acceptance number for each class. Many buyers set zero for critical defects.
SamplingRandom draw across cartons, and who chooses the cartons.
After a failSorting, rework, re-inspection, and who pays.
Defects found in a passHow they are replaced or repaired.

How does a sampling plan decide a batch?

Here is a simple illustration, with no figures from the tables. Say the plan for your batch size tells the inspector to draw a set number of units. It allows up to a set number of major defects in that sample. If the inspector finds that number or fewer, the batch is accepted under the plan. One more, and it is rejected. The sample size and the limits come from the agreed plan before anyone opens a carton. You can't draw ten pieces first and decide afterwards whether the batch passes.

Who decides whether a defect is critical, major or minor?

The contract should, before the inspection. If it doesn't, the argument moves to the factory floor, where the inspector decides on the day and each side pushes for the reading that suits it.

These examples are based on matters I have handled. Names, products, places, dates, amounts and other identifying details have been removed or changed. They show the kind of work involved. They don't promise any result.

Acting for a buyer

A random 10% check, with no rule for passing or failing the batch

A buyer had asked only for a random check of one tenth of the goods, with no rule for accepting or rejecting the batch. The buyer read AQL as the share of bad goods it would have to take. The supplier wanted every problem classed as minor. I had the inspector explain each classification with photos of the actual defects, and both sides then confirmed which problems affect safety, function or saleability. The sample size and the accept and reject numbers came from a fixed plan. A separate plan dealt with the defects found, covering sorting, rework and re-inspection, because an accepted batch still leaves defective pieces to fix. Once both plans were confirmed, the batch was inspected and corrected as agreed, and neither side changed the criteria again.

Questions from overseas buyers

If the plan allows zero critical defects, does a pass mean there are none?

No. It means none turned up in the sample. Units that weren't drawn may still have one. For safety-critical points, add a specific test or a full check of every unit.

Can the inspection company choose the inspection level on the day?

Only if your contract leaves it open. Then the report may follow a level you never expected, and a dispute about the result becomes a dispute about the method. Fix the standard, the level and the defect classes in the contract or the inspection booking.

Does the AQL in my contract set the supplier's warranty?

No. The AQL decides whether a batch passes inspection. The supplier's duty to deliver goods that meet the contract, and its warranty, are separate terms. Keep them in the contract.


I draft manufacturing agreements and quality schedules with the sampling plan written in →


Sources and translations
  • Standardization Law of the PRC (2017 revision), art. 2.
  • ISO 2859-1 and GB/T 2828.1 are cited by name only. I have not reproduced their sampling tables.

Translations are mine and unofficial.

Have a China-side question?

Tell us the product and the Chinese factory. Say whether you have a draft, a signed contract or orders already running, and which documents you have. The responsible lawyer replies within one calendar day. We will tell you where you stand and what your options are.

More about you and the Chinese company (optional)

Please do not send confidential documents, passwords, bank details or sensitive personal information in your first enquiry. See our privacy and confidentiality notice.