China sourcing glossary
What Are FAT and SAT? Factory and Site Acceptance Tests for Machines Bought From China
What is the difference between FAT and SAT?
| FAT | SAT | |
|---|---|---|
| Where | The supplier's factory | Your site, after installation |
| When | Before shipment | After installation and commissioning |
| Conditions | The factory's power, materials and set-up | Your power, materials, software links and environment |
| What it usually confirms | Configuration and the agreed performance under factory conditions | Performance in real use, at the agreed output |
| What the contract often ties to it | Release for shipment, a stage payment | Final acceptance, the balance, the start of the warranty |
A FAT pass can allow shipment. It doesn't by itself show the machine will reach the agreed output on your site. If the factory tests with ideal material and your material is different, the SAT is where that shows.
What should a FAT or SAT test protocol include?
Write the protocol before the contract is signed, or as a schedule to it. It usually covers:
- Test material. What the machine processes in the test, and who supplies it.
- Load. The load or output level, so an empty run can't count as a pass.
- Run time. How long the machine must run without stopping, set for this machine and its use.
- Pass criteria. Measurable figures such as output, accuracy, reject rate or energy use, with the method of measurement.
- Conditions. Power, utilities, temperature and other conditions, as close to real use as the test allows.
- Site readiness. What you must have ready for the SAT, and what happens if it isn't ready on the date.
- Records. Who attends, who signs the test record, and how faults are logged.
- Retests. How many, within what time, and who pays.
- Failure. What happens after the last failed retest, such as price reduction, refusal or a refund.
These examples are based on matters I have handled. Names, products, places, dates, amounts and other identifying details have been removed or changed. They show the kind of work involved. They don't promise any result.
Acting for a buyer
The supplier ran the machine empty and asked for final acceptance
On an equipment purchase I reviewed, the supplier ran only a no-load demonstration and then asked the buyer to sign final acceptance. The buyer's engineers cared about performance after continuous running. The factory said one successful demonstration was enough. I had both sides write down what each meant by a pass, and checked whether the test material, load, run time and conditions were close to real use. Tests that could only be done on site got their own date and duties to cooperate, with a rule for waiting if the site wasn't ready. Who confirms the test records, and how faults are logged and retested, were settled in advance. Payments were matched to the test stages, so no balance fell due before the machine had been proven. After the agreed tests and fixes, the buyer confirmed acceptance and paid each stage.
How should payments follow the tests?
Match each payment to the test that comes before it. A common pattern is a deposit, a payment after the FAT is confirmed in writing, and the balance after the SAT. Say that silence, or getting ready to ship, doesn't count as passing. My purchase contract page describes a contract where the balance waited for written confirmation of the FAT and two failed retests allowed a refund. That page also answers what to do if a machine passed in China and failed after installation.
Who can sign off a test?
Your engineers can confirm test results. Whether their signature can also give up a claim depends on their authority. Under Chinese law, what staff do within their job authority binds the company. Internal limits on that authority can't be raised against a counterparty acting in good faith (Civil Code art. 170). So write in the contract that a test record confirms results only. Final acceptance, and any waiver of claims, needs a named, authorised person.
Questions from overseas buyers
Does Chinese law define FAT and SAT?
No. They exist because the contract creates them. Without them, the general sale rules apply. The buyer inspects within the agreed period, or promptly if none is agreed (Civil Code art. 620), and notifies problems in time (art. 621).
Who pays if the SAT fails because of my site?
The contract should split the causes: an equipment defect, an installation problem, or site conditions you were meant to provide. Each needs its own answer on cost, a second visit and the retest date.
How long should the machine run in the test?
There is no single figure, so don't copy one from another contract. It depends on the machine and how you will use it. Long enough to show stable output under the agreed load is the usual aim, and the protocol should state it in hours or cycles.
I draft purchase contracts for standard machines, with FAT and SAT stages tied to payment →
Sources and translations
- Civil Code of the PRC (2020), arts. 170, 620 and 621.
Translations are mine and unofficial.