What Are FAT and SAT? Factory and Site Acceptance Tests for Machines Bought From China

What is the difference between FAT and SAT?

FATSAT
WhereThe supplier's factoryYour site, after installation
WhenBefore shipmentAfter installation and commissioning
ConditionsThe factory's power, materials and set-upYour power, materials, software links and environment
What it usually confirmsConfiguration and the agreed performance under factory conditionsPerformance in real use, at the agreed output
What the contract often ties to itRelease for shipment, a stage paymentFinal acceptance, the balance, the start of the warranty

A FAT pass can allow shipment. It doesn't by itself show the machine will reach the agreed output on your site. If the factory tests with ideal material and your material is different, the SAT is where that shows.

What should a FAT or SAT test protocol include?

Write the protocol before the contract is signed, or as a schedule to it. It usually covers:

These examples are based on matters I have handled. Names, products, places, dates, amounts and other identifying details have been removed or changed. They show the kind of work involved. They don't promise any result.

Acting for a buyer

The supplier ran the machine empty and asked for final acceptance

On an equipment purchase I reviewed, the supplier ran only a no-load demonstration and then asked the buyer to sign final acceptance. The buyer's engineers cared about performance after continuous running. The factory said one successful demonstration was enough. I had both sides write down what each meant by a pass, and checked whether the test material, load, run time and conditions were close to real use. Tests that could only be done on site got their own date and duties to cooperate, with a rule for waiting if the site wasn't ready. Who confirms the test records, and how faults are logged and retested, were settled in advance. Payments were matched to the test stages, so no balance fell due before the machine had been proven. After the agreed tests and fixes, the buyer confirmed acceptance and paid each stage.

How should payments follow the tests?

Match each payment to the test that comes before it. A common pattern is a deposit, a payment after the FAT is confirmed in writing, and the balance after the SAT. Say that silence, or getting ready to ship, doesn't count as passing. My purchase contract page describes a contract where the balance waited for written confirmation of the FAT and two failed retests allowed a refund. That page also answers what to do if a machine passed in China and failed after installation.

Who can sign off a test?

Your engineers can confirm test results. Whether their signature can also give up a claim depends on their authority. Under Chinese law, what staff do within their job authority binds the company. Internal limits on that authority can't be raised against a counterparty acting in good faith (Civil Code art. 170). So write in the contract that a test record confirms results only. Final acceptance, and any waiver of claims, needs a named, authorised person.

Questions from overseas buyers

Does Chinese law define FAT and SAT?

No. They exist because the contract creates them. Without them, the general sale rules apply. The buyer inspects within the agreed period, or promptly if none is agreed (Civil Code art. 620), and notifies problems in time (art. 621).

Who pays if the SAT fails because of my site?

The contract should split the causes: an equipment defect, an installation problem, or site conditions you were meant to provide. Each needs its own answer on cost, a second visit and the retest date.

How long should the machine run in the test?

There is no single figure, so don't copy one from another contract. It depends on the machine and how you will use it. Long enough to show stable output under the agreed load is the usual aim, and the protocol should state it in hours or cycles.


I draft purchase contracts for standard machines, with FAT and SAT stages tied to payment →


Sources and translations
  • Civil Code of the PRC (2020), arts. 170, 620 and 621.

Translations are mine and unofficial.

Official texts cited in this article.

Have a China-side question?

Tell us the product and the Chinese factory. Say whether you have a draft, a signed contract or orders already running, and which documents you have. The responsible lawyer replies within one calendar day. We will tell you where you stand and what your options are.